Project details
Client: KG Stockstadt landfill site, Seligenstädter Str., 63811 Stockstadt
Project sponsor: LRA Aschaffenburg, Waste Management, Bayernstr. 18, 63739 Aschaffenburg
Mission: Work phases 3-9 in accordance with Part VII HOAI, local construction supervision
Boundary conditions: Waste cover up to 20 m, existing shaft dilapidated
Remediation technology:
Shotcrete construction pit with a diameter of 5.50 m, depth approx. 20 m, dismantling of the existing shaft, removal of the new reinforced concrete shaft DN 1,800 as a drainage shaft with lining/sheathing made of polypropylene, installation of flushing lances and ring drainage.
Construction time, execution period: approx. 4 months, 2011
Project management: Dipl.-Ing. (FH) Jörg Kässinger
Technical support / local construction supervision: Dipl.-Ing. (FH) Wolfgang Edenberger, ICP Urbach